Wharton County residents continue to express opposition to Amazon building a 3,000-acre data center in the rural farm community located roughly an hour south of Houston.
Abbott announced his data center ban on Sept. 21. The Coastal Bend Groundwater Conservation District issued water permits to Amazon in May and earlier in September.
The CBGCD permits allow Amazon to tap millions of gallons of groundwater a year and don’t apply to millions of gallons of surface water the complex would need.
Amazon is building a 3,000-acre campus outside of Boling, about 10 miles southeast of Wharton. It says the complex will support at least 300 full-time jobs, with 150 becoming available by mid-2027. Construction will generate thousands of additional jobs.
Between 10-13 data center buildings are being built on the complex. Each is equivalent to the size of a Walmart Superstore.
Scarcity of water in…