137

Puerto Rico needed electricity. That urgency was real. Years of generation shortages and repeated blackouts made additional power a public priority. Against that backdrop, the Puerto Rico Electric Power Authority pursued a contract for up to 400 megawatts of temporary generation at the Aguirre Power Plant — a deal potentially worth nearly $5.9 billion over 10 years.

Urgency, however, does not eliminate the need for basic due diligence. A government can move quickly and still know who its contractors are, whether they can perform, who has authority to bind them, and why they were selected.

This contract failed that test.

The agreement listed Power Expectations, Enchanted Rock, and Reyes Contractor collectively as the seller. Then it unraveled over the most elementary question in contracting: Had one of those companies actually agreed to be there?

Enchanted Rock says it never…

Read more…