Michaelsen thought he had won. But when the TCEQ commissioners took up the question several months later, again they rejected all of the judge’s findings.
In a 19-page order issued in September, the commission concluded that “faults within 2.5 miles of its proposed disposal wells are not sufficiently transmissive or vertically extensive to allow migration of hazardous constituents out of the injection zone.” The old nearby oil wells, the commission found, “are likely adequately plugged and will not provide a pathway for fluid movement.”
“UEC demonstrated the proposed disposal wells will prevent movement of fluids that would result in pollution” of an underground source of drinking water, said the order granting the injection disposal permits.
“I felt like it was rigged, a setup,” said Michaelsen, holding his 4-inch-thick binder of research and records from the case….